- Monday 24 August
- 14:00 to 18:00
- GRAND AMPHITHEATRE (Access level 2)
- Delegates
Moderators: Ben Vanderwaal (CIGRE SC C5) and Trevor D. Hines (CIGRE SC C2)
Purpose of the workshop : to share experiences of significant technical and market disturbances that have occurred in the past 12-24 months.
- What happened? Type of disturbance?
- How did power systems, participants & institutions respond?
- How did markets and regulatory policy and settings perform?
- What observations/lessons learned were there?
Events that involved both power system and market disturbances are particularly welcome. However, disturbances impacting only one aspect are also welcome.
Presenters addressing the disturbance impacting both power system and market operations will be asked to coordinate their content to avoid duplication. For example, the event should be described only once.
Presentations:
1. Grid incident in Spain and Portugal on 28 April 2025
2. Chile blackout on 25 February 2025
3. From Cyber-Physical Disturbance to Transformer Asset Loss: Risk Consequences, Material Resilience and NIS2/CER Policy Lessons
4. Georgia system blackout on 19 April 2025
5. 16.5 GW Load Reduction and Delayed Recovery event in India on 17 June 2024
6. North Hyde Substation Outage (Heathrow Airport Incident on 20 March 2025
7. ...